We were the lead consultant for this turn-key design and construction solution for the installation of a new stand-alone life safety generator. The project included disconnecting the building’s life safety systems from a Verizon Central Office generator while insuring power to their critical facility remained uninterrupted.

Our team provided a new concrete pad and modified duct work, to accommodate the new 250kW, 60 Hz diesel powered emergency generator. All of the building life safety loads were transferred to the new generator and the project was delivered successfully.

We provided start-up and testing procedures of the system, completing commissioning to ensure the generator was operating as designed and intended.