99 High street

Our team has been the base building engineer at this 32-story building since 2009. Our work has included upgrading the boiler and chiller, helping the owner (TIAA-CREF) to save over $650,000 a year in energy costs. We have also upgraded the existing MEP/FP infrastructure, which expanded the retail opportunities at the building.

For the repositioning of the lobby, we relocated the MEP systems to accommodate for the new double-height glass façade. The challenge for our team was to relocate the MEP systems so that they were not visible, but still maintain the functionality.

Following these infrastructure upgrades, we have worked on over 35 workplace fit-out projects in the building.