Disaster Recovery Site

Upgrade and expansion of a disaster recovery site

Disaster recovery facilities are really interesting to design – they are often not being fully used, but need to be absolutely reliable in the event that a company’s main site is down. For this financial client, we provided a needs analyses and then based on our finding prepared engineering documents the addition of twelve new server racks in the existing space. We also designed the MEP systems for the facility’s new mechanical room. Our work included developing HVAC, UPS, generator and ATS pre-purchase specs, and managing vendor selection and bid leveling.

The electrical capacity in the new space was increased. The existing 60 kva UPS was replaced with a 150 kva UPS, and the 150 kw generator was replaced with 350 kw generator. From a mechanical perspective, the existing air cooled CRAC units were replaced with two water-cooled systems running on 30% glycol solution connected to roof-top dry coolers. Thirty tons of cooling was distributed to the server room, and eight tons to the mechanical room.  In addition, we designed the modification to the existing server room ANSUL fire protection system.

The site remained active during construction, which impacted our design as we included careful risk management plans and phasing plans in our documentation.

Project Type
Mission Critical
Client

Project Services