Design and commissioning for a corporate re-stack

Our team has worked with Akamai on the fit-out and re-stack of three floors of their space. The project included an office fit-out, IDF and computer lab spaces, executive offices and conference rooms with extensive AV requirements. The project required attention to detail, and close coordination to ensure that our design worked successfully with the audio visual systems and specialty finishes.

After the systems we designed were installed, our team commissioned the project. We prepared a commissioning plan included as part of the construction contract documents, provided oversight throughout construction, and then conducted final inspections and testing to ensure that all systems worked as designed.  The equipment that we tested included VAV’s, FPT’s, outdoor air fans, and heat pumps.

Project Type
Interiors
Client
Location
Cambridge, MA
Architect
Packard Design
Square Footage
58,000

Project Services

Due Diligence Study

Surveyed buildings and spaces to understand existing MEP/FP/IT systems.

Electrical (Interiors)

Prepared electrical lighting drawings for fixture circuiting, specification and switching. Prepared power drawings with circuiting, panels, transformers, exit signs and emergency lighting.

Fire Protection (Interiors)

Prepared drawings showing distribution piping and locations of sprinkler heads, preaction and/or FM 200 systems.

Mechanical (Interiors)

Designed HVAC systems including transfer fans, environmental requirements, controls and management systems.

Plumbing (Interiors)

Designed plumbing fixture locations and rough-in requirements.